Updates on Abbot’s House
As earlier reported, the construction of the Abbot’s House is in progress, and the skeleton of the building will be completed in the first week of November .
The next stage of the building is to cast a ring beam that will hold a grass-thatched roof. Thereafter, the house shall be roofed and some of the materials for the roof have been booked.
Some parts of the building like the basement, have been finished and fittings are already fixed.
Also, a water tank has already been installed that will supply water to the entire building.